Investinženjering d.o.o. signed a framework agreement for complete supervision of construction of gas distribution system (GDS) for County of Šibenik-Knin.
Supervision is provided for construction of:
- high-pressure gas-pipeline, including PEHD pipe for optical cable (length of 9,5 km );
- mid-pressure gas-pipeline (length of 12 km) and household connections;
- odorization station OS Knin;
- measuring reduction/odorization station MRS/OS Šibenik.
Supervision includes main supervisory engineer, civil works, mechanical and welding, geotechnical, geomechanical and ecological supervisory engineers, as well as supervision of electro and instrumentation works.
Expected duration of works is one year. Expected completion of works: 15.09.2014