Procurement & Contract Administration for container Terminal Brajdica-Rijeka Container Terminal Brajdica pier extension project (328m new pier / 101.000m2 warehouses). GI prepared the Tender documents and assisted in the procurement process, which was done according to the World Bank rules. GI acted as the FIDIC Engineer (red book) and provided supervisory servics.

Procurement & Contract Administration

The Project consists of four components marked with letters A, B, C and D.

Component A (Pier extension) refers to works necessary for extension of the pier of Container Terminal Brajdica i.e. quay wall in length of 328 m with pier surface for loading and unloading of containers. Total size of open warehouse space for manipulation and storage of containers is approximately 50 000 m².

Component B (Entrance and Exit Gate) refers to works necessary for the construction of Administration building of Container Terminal Brajdica, structures for control and protection of primary entrance, parking area for heavy and personal vehicles and storage area for frigo-containers. Total size of area under construction in this component is approximately 16.000 m².

Component C (Railway terminal) refers to works necessary for the construction of new Brajdica railway terminal and reconstruction of approaching roads and approaching railways to terminal through port area. Total size of area under construction in this component should be approximately 13 400 m².

Component D (Maintenance and other services) refers to works necessary for the construction of Brajdica Container Terminal closed warehouse for loading and unloading of containers. Total size of area under construction within this component should be approximately 21 550 m².

Infrastructure

Procurement and Contract administration

  • Services rendered

    Procurement & Contract Administration, Engineering Supervision
  • Project size

    328m new pier / 101.000m2 warehouses
  • Project value

    33 million €
  • Project period

    2010 - 2013
  • Investor

    Port of Rijeka Authority